Arena Simulation Tested 42 Scenarios Before an $18M Packaging Upgrade

Engineering firm Burns & McDonnell used Rockwell Software Arena simulation to test 42 equipment-replacement scenarios for an unnamed food manufacturer's three packaging lines before an $18 million upgrade. Rockwell Automation's 2015 case study says the upgrade exceeded the 10 percent capacity-increase goal and 80 percent less downtime than competitor projections. It does not say what capacity the plant reached, what downtime it measured afterward, or whether any AI was involved.

Maintained by Peter Korpak, Lead EditorHow evidence is checked
$18 millionPackaging upgrade cost
10%Capacity-increase goal, exceeded
80% lessDowntime vs competitor projections

Source-reported figures (cited source: Rockwell Automation)

What the food manufacturer was trying to fix

A packaged-food maker more than a century old had outgrown its legacy packaging equipment, according to the Rockwell Automation case study published May 27, 2015. Rockwell has since removed the page; this summary follows the Internet Archive copy captured on January 20, 2026. Reliability problems limited line speed and output across three main packaging lines of up to nine key machines each, though not every machine underperformed. The upgrade had to deliver a 10 percent capacity increase with minimal interruption to production, so engineering firm Burns & McDonnell first had to find which machines to keep. The source does not name the manufacturer or give baseline speeds, downtime, or output.

How Burns & McDonnell used Arena simulation

Burns & McDonnell used Rockwell Software Arena simulation to test packaging-line changes before any equipment was bought, without plant downtime. Rockwell Automation says the team collected plant capacity, production schedules, equipment reliability data and equipment rates, then built a range for each machine. To check the model, 150 days of simulation output were compared with six months of historical plant data, and key equipment and line reliability results were within 0.25 percent of each other. The team and manufacturer then defined 42 scenarios, including replacing the bundler, capper, tray former or palletizer on each line individually and replacing all four. Each scenario ran low, mid and high simulations to establish an average over 120 days of production. The source describes what-if simulation, not AI or machine learning.

Capacity and downtime reported by Rockwell

Rockwell Automation reports these outcomes:

  • Upgrade: after comparing the 42 simulations, the team recommended replacing specific machinery on each of the three main lines, and an $18 million packaging upgrade followed.
  • Capacity: the investment "exceeded the manufacturer's original goal of a 10 percent increase in production capacity." Rockwell's summary instead says the plant achieved a 10 percent increase, and the achieved figure is not given.
  • Downtime: 80 percent less than competitor projections, which is a comparison with projections, not with the plant's earlier downtime.

This is a vendor-published 2015 account. It gives no measured capacity, payback, or post-upgrade downtime,.

Checks to make before a simulation-led upgrade

Before acting on a simulation-led recommendation, check three things:

  • Ask how the model was validated. Here, 150 days of simulation were compared with six months of plant history. Check which of your own data (rates, reliability, schedules) the model needs, and test it against your history before trusting a scenario ranking.
  • Ask how the 42 scenarios led to the final equipment list, what capacity each option projected, and what the plant measured after commissioning. The source gives no achieved figure.
  • Ask what "80 percent less downtime than competitor projections" compares, who made those projections, and what downtime the plant recorded after the upgrade.

This record appears in the production-planning evidence matrix. For how simulation differs from a digital twin, see the digital twin guide.

Evidence for the Arena simulation and packaging upgrade

Reported outcome
Upgrade exceeded a 10% capacity goal; achieved figure not given
Directory published
Source published

Limitation: The cited source does not identify the company.

Share:

Details

AI Technology
Not established by the source
Company Size
Not reported by source
Company
Food Manufacturer