Mexican oilfield operator Nuvoil needed to design a complex gas conditioning plant control system under a compressed 9-month timeline to capture value from gas that was previously being flared.
Rockwell Automation Integrated Architecture with Allen-Bradley ControlLogix Process Controllers managing 3,000+ data points for the gas conditioning plant. Implemented by CAM Integrated Solutions.
Plant up and running in 9 months, at full capacity in 12.4 months. Processes approximately 320,000 cubic feet of gas daily. Generates approximately $200,000 in revenue per day.
Integrated process control on Allen-Bradley ControlLogix can convert previously flared oilfield gas into $200K daily revenue, with complex gas conditioning plants managing 3,000+ data points deployable in under 10 months.