Mitsubishi Chemical Brazil Plant: Modular Controls, 3-4 Months Saved

Mitsubishi Chemical Performance Polymers launched a greenfield resin plant in Brazil using a modular extrusion control system that Apex built and tested in Indiana before shipment. Rockwell Automation's 2017 case study reports that deployment time fell by three to four months and the I/O count fell 70 percent with EtherNet/IP. The account stops at control hardware, historian data and alarms; it reports no AI method, cost, production figure, or quality result.

Maintained by Peter Korpak, Lead EditorHow evidence is checked
3-4 monthsDeployment time saved
70%I/O count reduction with EtherNet/IP

Source-reported figures (cited source: Rockwell Automation)

What Mitsubishi Chemical Performance Polymers was trying to fix

Mitsubishi Chemical Performance Polymers (MCPP) planned a greenfield resin plant north of Sao Paulo to supply airbag manufacturers after a 2014 Brazilian law required airbags on all new vehicles. Rockwell Automation's July 21, 2017 case study says MCPP wanted production to start close to the requirement, and the rainy season had pushed site work somewhat behind schedule. The extrusion system had to make up to about 10 million pounds of resin a year, match MCPP's quality management elsewhere, and give operators visibility into quality. MCPP also wanted remote access for U.S. staff and outside experts, given limited local technical support. Rockwell has since removed the page; this summary follows the Internet Archive copy captured on January 20, 2026.

How MCPP built the Brazil plant's control system

MCPP evaluated two vendors and chose Apex Engineering and its subsidiary Apex Control Specialists, a Rockwell Automation Recognized System Integrator. According to Rockwell Automation, Apex designed and built its modular extrusion system in Evansville, Indiana while the Brazilian plant was under construction, and MCPP staff joined a week of testing before shipment. The control center uses a CompactLogix PLC, PowerFlex 755 AC drives and solid-state relays. FactoryTalk Historian collects thousands of data points, FactoryTalk View and VantagePoint EMI software let workers manage recipes and monitor processes, and EtherNet/IP shares the data plant-wide and with remote experts. Add-on instructions make later changes plug-and-play. The source describes PLC control, historian data and setpoint alarms. It does not describe AI or machine learning.

Deployment and wiring results reported by Rockwell

Rockwell Automation reports these outcomes at the Brazil plant:

  • Deployment time: the modular system cut facility deployment time by three to four months. The text says installation took about one month and saved "as much as four months."
  • Wiring: EtherNet/IP reduced the I/O count by 70 percent. The source does not give the baseline count.
  • Early downtime: the plant manager says remote support reduced some early downtime incidents from days into hours.
  • Changes: a new feeder can be added in as little as 10 minutes.

This is a vendor-published 2017 account quoting the plant manager. It gives no cost, production or quality results and no comparison schedule.

Checks to make before a modular control build

A modular control build raises three questions worth settling before you sign:

  • Ask what the three-to-four-month saving is measured against. The source gives "as much as four months" and a one-month installation, but not the schedule of a conventional build. Request that comparison plan.
  • Test remote access before you rely on it. MCPP's U.S. staff and Apex diagnosed problems remotely, which the source credits with shortening early downtime. Ask who can reach which data points, how access is secured and logged, and what the plant does when the link is down. The source does not cover these points.
  • Check how quality visibility is built. The account describes trends and min/max setpoint alarms, with no quality result. Ask which quality parameters are alarmed, how limits were set, and how alarms connect to product quality.

For related reading, see the Chemicals industry hub and the manufacturing system integration guide.

Evidence for MCPP's modular control deployment

Reported deployment saving
3-4 months faster; I/O count down 70%
Directory published
Source published

Share:

Details

Industry
Chemicals
AI Technology
Not established by the source
Company Size
Not reported by source

Have a similar implementation?

Share your customer's AI results and link it to your vendor profile.