Achieving the Seemingly Impossible: Greenfield Global Plant Commissioning
Greenfield Global deployed Digital Twin for Process Optimization in Pharmaceuticals. As reported by rockwellautomation.com: 4 weeks on schedule fat testing duration.
Source-reported figures (cited source: rockwellautomation.com)
What Greenfield Global was trying to fix
Greenfield Global was commissioning a new pharmaceutical-grade ethanol production facility in Ireland in 2020 when COVID-19 lockdown restrictions made it impossible for engineers to travel to site for traditional Factory Acceptance Testing (FAT) and commissioning activities. In the pharmaceutical sector, ethanol is a regulated ingredient in sanitizers, excipients, and solvent applications, and demand had surged during the pandemic precisely when the project faced its most severe logistical constraints. Delays to commissioning would have meant lost revenue at a moment of peak market demand, and jeopardized the project's full-production timeline.
What Greenfield Global deployed
Greenfield Global and system integrator Alpha Automation deployed Rockwell Automation's PlantPAx 5.0 Distributed Control System, using its built-in remote commissioning and virtual FAT capabilities, a digital twin approach that allowed engineers to validate control logic and I/O configurations without being physically present on site. The PlantPAx 5.0 platform enabled remote access to the control environment, so Rockwell Automation and Alpha Automation engineers could conduct acceptance testing, troubleshoot sequences, and sign off on functionality from off-site locations across different countries. This virtual commissioning workflow replaced what would traditionally require weeks of on-site presence and ran within the plant's process control architecture from the outset.
Results
The project hit every major milestone despite pandemic-era constraints. FAT testing was completed on schedule within 4 weeks, and the Ireland facility went live in October 2020 — shipping product to customers before year-end. Total time from commissioning start to full production came in at under 10 months. Key outcomes included:
- FAT completed remotely and on schedule, with no requirement for international travel
- Plant operational and revenue-generating before end of 2020
- Full production capacity reached within 10 months of project start
- Pandemic-era restrictions did not require timeline concessions
Key Takeaways
- Remote commissioning capability should be a baseline requirement, not an emergency fallback: PlantPAx 5.0's virtual FAT tools made distributed testing work for this process plant.
- System integrator selection matters: Alpha Automation's familiarity with the PlantPAx ecosystem was critical to executing remote FAT without on-site escalation.
- Digital twin investment pays off under constraint: the virtual commissioning environment reduced travel dependencies and compressed the timeline rather than extending it.
- For pharmaceutical and regulated-process facilities, establishing remote-accessible control architecture early in design avoids costly retrofits when access is restricted.
- Tight deadlines in high-demand markets justify the premium for modern DCS platforms with integrated remote tooling.
Evidence for Greenfield Global's Process Optimization deployment
- Reported outcome metrics
- 2 cited below
- Cited source
- rockwellautomation.com
- Last updated
Vendor
Details
- Industry
- Pharmaceuticals
- Use Case
- Process Optimization
- AI Technology
- Digital Twin
- Company Size
- Enterprise
- Company
- Greenfield Global
Have a similar implementation?
Share your customer's AI results and link it to your vendor profile.
Submit a case study →